2018 Road Program

2018 Road Program

Road paving has began around the Municipality.  Please check back frequently as the schedule is updated.

Mill:

Day 1 (5/10) – Janet, Dumbarton (25% still remains)

Day 2 (5/11) – finish Dumbarton, Rolling Green, Lytle, Lindemere

Day 3 (5/14) – finish Lindemere if not complete, Orchard, Sherwood

Day 4 (5/15) – finish Sherwood if not complete, Spartan

 

Pave:

Day 1 (5/11) – Janet binder, Janet wearing, Dumbarton leveling

Day 2 (5/14) – Dumbarton wearing, Rolling Green Binder, Rolling Green wearing, Lytle wearing

Day 3 (5/15) – complete unfinished from day before, Lindemere wearing, Orchard binder

Day 4 (5/16) – complete unfinished from day before, Sherwood binder, Sherwood wearing, Orchard wearing

Day 5 (5-17) – complete unfinished from day before, Spartan leveling, Spartan wearing

 

Click here to download a schedule